Wash. Admin. Code § 173-145-040
The county engineer of the county within which the maintenance project is located shall certify that the CFCMP has been completed and adopted by the appropriate local authority or is being prepared. Comprehensive flood control management plans, and any revisions to the plans, must be approved by ecology, in consultation with the department of fish and wildlife. The CFCMP must be completed and adopted within three years of the date that it is certified as being prepared. If, after the three-year period has elapsed, such a plan has not been completed and adopted, the appropriate local authority may not make grants to the county for flood control maintenance projects until the CFCMP is completed and adopted by the appropriate local authority. During the three-year period, projects within a drainage area, designated as the CFCMP study area, may be funded as part of a phased project plan: Provided, That preliminary studies for the CFCMP have been conducted to identify the one-hundred-year frequency flood plain problem areas and factors contributing to flooding: And provided further, That the proposed projects have been prioritized to achieve the greatest efficiency in flood control for the overall CFCMP study area. These limitations on grants may not preclude allocations for emergency purposes made under RCW 86.26.060. The appropriate local authority may require the applicant to fully or partially fund the preparation of the CFCMP. The plan must include:
(1) Determination of the need for flood control work.
(2) Alternative flood control work.
(3) Identification and consideration of potential impacts of instream flood control work on the following instream uses and resources.
(5) Conclusion and proposed solution(s). The CFCMP must be finalized by the following action from the appropriate local authority:
[Statutory Authority: RCW 86.26.105. WSR 01-02-006 (Order 00-13), § 173-145-040, filed 12/21/00, effective 1/21/01. Statutory Authority: Chapter 86.26 RCW. WSR 87-04-022 (Order 86-36), § 173-145-040, filed 1/28/87; WSR 85-14-002 (Order DE 85-10), § 173-145-040, filed 6/21/85.]