Wash. Rev. Code § 60.90.060
(1) After a wage claim for which a wage lien has been recorded as to real property has been commenced in any court, but no later than eight months after the recording of the wage lien, the wage claimant or the claimant's assignee must file with the auditor of each county in which the property is situated a notice of the pendency of the wage claim, containing:
[ 2021 c 102 s 7.]