Wash. Rev. Code § 43.158.120
(1) A project proponent may submit a written request to the department of ecology pursuant to RCW 43.158.140 and a local government development agreement to support local government actions pursuant to RCW 43.158.130 for participation in a fully coordinated permitting process. To be eligible to participate in the fully coordinated permit process:
(a) The project proponent must:
(3) For a fully coordinated permitting process, the department of ecology must serve as the main point of contact for the project proponent and participating agencies with regard to coordinating the permitting process for the project as a whole. Each participating permit agency must designate a single point of contact for coordinating with the department of ecology. The department of ecology must keep a schedule identifying required procedural steps in the permitting process and highlighting substantive issues as appropriate that must be resolved in order for the project to move forward. In carrying out these responsibilities, the department of ecology must:
(b)
(4) Within 30 days, or longer with agreement of the project proponent, of the date that the department of ecology determines a project is eligible for the fully coordinated permitting process, the department of ecology shall convene a work plan meeting with the project proponent, local government, and the participating permit agencies to develop a coordinated permitting process schedule. The work plan meeting agenda may include any of the following:
(11)
[ 2023 c 230 s 206.]
Findings—Intent—2023 c 230: See note following RCW 43.394.010.