Wash. Rev. Code § 39.116.020
(1)
(a) Beginning July 1, 2025, an awarding authority must require in all newly executed construction contracts that the selected firm for a construction contract for a covered project larger than 100,000 gross square feet submit the following data for each covered product used before substantial completion, including at a minimum:
(3)
(a) Beginning July 1, 2025, an awarding authority must require in all newly executed construction contracts that the selected firm for a construction contract for a covered project larger than 100,000 gross square feet to ask their suppliers to report for each covered product used before substantial completion, including at a minimum:
[ 2024 c 344 s 3.]