Wash. Rev. Code § 35.99.030
(1) Cities and towns may require a service provider to obtain a master permit. A city or town may request, but not require, that a service provider with an existing statewide grant to occupy the right-of-way obtain a master permit for wireline facilities.
(b) Where a city or town requires a master permit, the city or town shall act upon a complete application within one hundred twenty days from the date a service provider files the complete application for the master permit to use the right-of-way, except:
(2) A city or town may require that a service provider obtain a use permit. A city or town must act on a request for a use permit by a service provider within thirty days of receipt of a completed application, unless a service provider consents to a different time period or the service provider has not obtained a master permit requested by the city or town.
(5) A city or town shall:
(6) A service provider shall:
(7) Nothing in this section shall be construed as:
[ 2000 c 83 s 3.]