A. The VESMP authority shall inspect the land-disturbing activity during construction for:
- 1. Compliance with the approved erosion and sediment control plan;
- 2. Compliance with the approved stormwater management plan;
- 3. Development, updating, and implementation of a pollution prevention plan; and
- 4. Development and implementation of any additional control measures necessary to address a TMDL.
B. The VESMP authority shall conduct periodic inspections on all projects during construction. The VESMP authority shall either:
- 1. Provide for an inspection during or immediately following initial installation of erosion and sediment controls, at least once in every two-week period, within 48 hours following any runoff producing storm event, and at the completion of the project prior to the release of any performance bonds; or
2. Establish an alternative inspection program that ensures compliance with the approved erosion and sediment control plan. Any alternative inspection program shall be:
- a. Approved by the department prior to implementation;
- b. Established in writing;
- c. Based on a system of priorities that, at a minimum, address the amount of disturbed project area, site conditions, and stage of construction; and
- d. Documented by inspection records.
C. The VESMP authority shall establish an inspection program that ensures that permanent stormwater management facilities are being adequately maintained as designed after completion of land-disturbing activities. Inspection programs shall:
- 1. Be approved by the department;
- 2. Ensure that each stormwater management facility is inspected by the VESMP authority or the VESMP authority's designee, not to include the owner, except as provided in subsections D and E of this section, at least once every five years; and
- 3. Be documented by records.
- D. The VESMP authority may utilize the inspection reports of the owner of a stormwater management facility as part of an inspection program established in subsection C of this section if the inspection is conducted by a person who is licensed as a professional engineer, architect, landscape architect, or land surveyor pursuant to Article 1 (§ 54.1-400 et seq.) of Chapter 4 of Title 54.1 of the code of Virginia; a person who works under the direction and oversight of the licensed professional engineer, architect, landscape architect, or land surveyor; or a person who holds an appropriate certificate of competence from the department.
- E. If a recorded instrument is not required pursuant to 9VAC25-875-130, a VESMP authority shall develop a strategy for addressing maintenance of stormwater management facilities designed to treat stormwater runoff primarily from an individual residential lot on which they are located. Such a strategy may include periodic inspections, homeowner outreach and education, or other method targeted at promoting the long-term maintenance of such facilities. Such facilities shall not be subject to the requirement for an inspection to be conducted by the VESMP authority.
Statutory Authority
§ 62.1-44.15:28 of the Code of Virginia.
Historical Notes
Derived from Virginia Register Volume 40, Issue 8, eff. July 1, 2024; amended, Virginia Register Volume 41, Issue 23, eff. August 14, 2025.