9 Va. Admin. Code § 25-580-85
A. To properly operate and maintain UST systems, not later than January 1, 2021, owners and operators must meet one of the following:
1. Conduct a walkthrough inspection that, at a minimum, checks the following equipment as specified below:
a. Every 30 days (Exception: spill prevention equipment at UST systems receiving deliveries at intervals greater than every 30 days may be checked prior to each delivery):
b. Annually:
B. Owners and operators must maintain records (in accordance with 9VAC25-580-120) of operation and maintenance walkthrough inspections for one year. Records must include a list of each area checked, whether each area checked was acceptable or needed action taken, a description of actions taken to correct an issue, and delivery records if spill prevention equipment is checked less frequently than every 30 days due to infrequent deliveries.
NOTE: The following code of practice may be used to comply with subdivision A 2 of this section: Petroleum Equipment Institute Recommended Practice RP 900, Recommended Practices for the Inspection and Maintenance of UST Systems.
§§ 62.1-44.15 and 62.1-44.34:9 of the Code of Virginia; 42 USC § 6901 et seq.; 40 CFR Parts 280 and 281.
Derived from Virginia Register Volume 34, Issue 1, eff. January 1, 2018; Errata, 34:4 VA.R. 503 October 16, 2017; amended, Virginia Register Volume 39, Issue 5, eff. November 23, 2022.