Va. Code Ann. § 56-603
As used in this chapter:
6. Enhanced leak detection and repair program costs. Such costs shall include the costs of operating an enhanced leak detection and repair program.
"Enhanced leak detection and repair program" means a program that is designed to allow a natural gas utility to deploy advanced leak detection technologies to more accurately identify active leaks as part of the natural gas utility's leak management program and to prioritize the repair of leaks that present a risk to safety or the environment. A natural gas utility may amend its SAVE plan to include an enhanced leak detection and repair program by filing an application to amend its previously approved SAVE plan, as set forth in subsection B of § 56-604.
"Investment" means costs incurred on eligible infrastructure replacement projects including planning, development, and construction costs; costs of infrastructure associated therewith; and an allowance for funds used during construction. In calculating the allowance for funds used during construction, the Commission shall use the natural gas utility's actual regulatory capital structure as determined in subdivision 1 of the definition of eligible infrastructure replacement costs.
"Natural gas utility" means any investor-owned public service company engaged in the business of furnishing natural gas service to the public.
"Natural gas utility facility replacement project" means the replacement of storage, peak shaving, transmission or distribution facilities used in the delivery of natural gas, or supplemental or substitute forms of gas sources by a natural gas utility.
"SAVE" means Steps to Advance Virginia's Energy Plan.
"SAVE plan" means a plan filed by a natural gas utility that identifies proposed eligible infrastructure replacement projects and a SAVE rider.
"SAVE rider" means a recovery mechanism that will allow for recovery of the eligible infrastructure replacement costs, through a separate mechanism from the customer rates established in a rate case using the cost of service methodology set forth in § 56-235.2, or a performance-based regulation plan authorized by § 56-235.6.
"Commission" means the State Corporation Commission.
"Eligible infrastructure replacement" means natural gas utility facility replacement projects that: (i) enhance safety or reliability by reducing system integrity risks associated with customer outages, corrosion, equipment failures, material failures, or natural forces; (ii) do not increase revenues by directly connecting the infrastructure replacement to new customers; (iii) reduce or have the potential to reduce greenhouse gas emissions; (iv) are commenced on or after January 1, 2010; and (v) are not included in the natural gas utility's rate base in its most recent rate case using the cost of service methodology set forth in § 56-235.2, or the natural gas utility's rate base included in the rate base schedules filed with a performance-based regulation plan authorized by § 56-235.6, if the plan did not include the rate base. "Eligible infrastructure replacement" includes natural gas utility facility replacement projects that are identified as a result of an enhanced leak detection and repair program.
"Eligible infrastructure replacement costs" includes the following:
2010, cc. 142, 514; 2022, cc. 728, 759.