Va. Code Ann. § 56-585.1:8
A. As used in this section:
"Host account" means the premises on which a municipal customer-generator's electrical generating facility is located.
"Municipal customer-generator" means a municipality that owns or operates, or that contracts with other persons to own or operate, an electrical generating facility that (i) uses as its total source of fuel renewable energy as defined in § 56-576, (ii) has a generating capacity of not more than three megawatts, (iii) is located on land owned or leased by the municipality within the municipality and is connected to the municipality's wiring on the municipality's side of its interconnection with the utility, (iv) is interconnected and operated in parallel with the utility's transmission and distribution facilities, and (v) is intended primarily to offset all or part of the municipal customer-generator's own electricity requirements. The capacity of any generating facility installed under this section, other than a generating facility located on airports, landfills, parking lots and garages, wastewater treatment sites, parks, post-mine land, or a reservoir that is owned, operated, or leased by the municipality, shall not exceed the same limitation established with respect to an eligible customer-generator as set forth in the definition of such term in subsection B of § 56-594.
"Municipality" means any county, city, or town in the Commonwealth, other than a municipality that owns and operates its own electric utility, or any authority created pursuant to the Park Authorities Act (§ 15.2-5700 et seq.).
"Net energy metering" means measuring the difference, over the net metering period, between (i) electricity supplied to a municipal customer-generator from the electric grid and (ii) the electricity generated and fed back to the electric grid by the municipal customer-generator.
"Net metering period" means the 12-month period following the date of final interconnection of the municipal customer-generator's system with its utility and each 12-month period thereafter.
"Phase I Utility" and "Phase II Utility" have the same meaning as defined in § 56-585.1:3.
"Utility" means a Phase I Utility or Phase II Utility.
B. The Commission shall require each Phase I Utility to submit a proposal to the Commission to conduct a pilot program for municipal net energy metering in accordance with the following terms, conditions, and restrictions:
C. The Commission shall require each Phase II Utility to submit a proposal to the Commission to conduct a pilot program for municipal net energy metering in accordance with the following terms, conditions, and restrictions:
D. Any pilot program conducted under this section shall require that:
2. If conducted by a Phase I Utility, the credit for excess electricity, to the extent possible, shall be prioritized to be directed to accounts at buildings or facilities of the public school division of the municipality before the credit is directed to any of the municipality's target accounts.
Any pilot program conducted pursuant to this section shall not limit the current authority of any municipality to participate in any other net energy metering program.
Neither jurisdictional customers nor non-jurisdictional customers, including those that are members of a joint powers association representing member units of a political subdivision of the Commonwealth, that do not participate in a pilot program under this section shall bear any costs associated with participation in such pilot program by a participating host municipal customer-generator and participating target municipal customer.
2019, cc. 746, 747; 2022, c. 388.