Va. Code Ann. § 56-585.1:3
A. As used in this section:
4. Has a generating capacity of:
b. More than two megawatts if not more than two megawatts of the output from the electrical generation facility is selected in an investor-owned utility's RFP for dedication to its pilot program.
"Generating capacity" means an electrical generation facility's nameplate rated capacity measured in direct current megawatts.
"Investor-owned utility" means an electric utility that is a Phase I Utility or a Phase II Utility.
"Low-income community" means a census tract within the Commonwealth designated by the U.S. Department of Housing and Urban Development in 2019 or any year thereafter as a qualified census tract for purposes of the Low-Income Housing Tax Credit pursuant to § 42 of the Internal Revenue Code.
"Participating generating facility" means an eligible generation facility that is selected by an investor-owned utility through its RFP for inclusion in its pilot program.
"Participating third party" means, for investor-owned utilities, a Virginia nonresidential-class customer, an affiliate, a solar development entity, or a nonjurisdictional customer that takes on the obligation, as part of a variable-output contract, of pilot program costs not recovered through the voluntary companion rate schedule as specified in subdivision B 8.
"Participating utility" means (i) each investor-owned utility and (ii) any utility consumer services cooperative that elects to conduct a pilot program under subsection C.
"Phase I Utility" means an investor-owned incumbent electric utility that was, as of July 1, 1999, not bound by a rate case settlement adopted by the Commission that extended in its application beyond January 1, 2002.
"Phase II Utility" means an investor-owned incumbent electric utility that was, as of July 1, 1999, bound by a rate case settlement adopted by the Commission that extended in its application beyond January 1, 2002.
"Pilot program" means a community solar pilot program conducted by a participating utility pursuant to this section following approval by the Commission, under which the participating utility sells electric power to subscribing customers under a voluntary companion rate schedule and the participating utility generates or purchases electric power from participating generation facilities selected by the participating utility.
"Pilot program costs" means all of a participating utility's identified, projected, and actual costs of its pilot program, including costs for (i) purchased power; (ii) renewable and other environmental attributes; (iii) transmission and distribution services; (iv) generating capacity and energy balancing; (v) RFP process costs; (vi) administrative and marketing charges; (vii) capital costs and operations and maintenance expenses related to building, owning, and operating eligible generating facilities; and (viii) a reasonable margin, which margin shall be the weighted average cost of capital.
"Pilot program period" means the three-year period ending three years following the date the first subscription is entered into by a customer.
"RFP" means the request for proposal process conducted by an investor-owned utility.
"Small eligible generation facility" means an eligible generation facility with a generating capacity of less than 0.5 megawatt.
"Solar development entity" means a business entity organized primarily for the purpose of proposing, developing, constructing, purchasing, or selling at wholesale all or part of the output of an eligible generation facility. A solar development entity may be organized in any form and may be a special purpose entity.
"Utility aggregation cooperative" has the same meaning ascribed to "cooperative" in § 56-231.38.
"Utility consumer services cooperative" has the same meaning ascribed to "cooperative" in § 56-231.15.
"Voluntary companion rate schedule" means a rate schedule approved by the Commission upon application by a participating utility that provides for the recovery of the pilot program costs by the participating utility.
"Eligible generation facility" means an electrical generation facility that:
B. Notwithstanding the provisions of subsection B of § 56-234 and §§ 56-249.6 and 56-585.1, each investor-owned utility shall conduct a pilot program for retail customers as follows:
2. An investor-owned utility shall select eligible generating facilities for dedication to its pilot program through an RFP process, under which process:
b. Each RFP shall:
5. An investor-owned utility shall have the option of increasing the amount of generating capacity of the eligible generating facilities in its pilot program above the amount most recently approved by the Commission, in such increments as the investor-owned utility elects, as follows:
C. Notwithstanding the provisions of subsection B of § 56-234 and §§ 56-249.6 and 56-585.1, upon application of a utility consumer services cooperative the Commission shall review a proposal submitted by the cooperative for a voluntary companion rate schedule. If the Commission finds that the proposal is reasonable and prudent, it shall approve the voluntary companion rate schedule for the cooperative to conduct a pilot program pursuant to this section. No utility consumer services cooperative shall be required to conduct a pilot program pursuant to this section. In making an application to the Commission pursuant to this subsection, a utility consumer services cooperative shall have flexibility to design its voluntary companion rate schedule in a manner that, notwithstanding anything to the contrary in this section, provides the cooperative the ability to:
2017, c. 580; 2019, cc. 742, 763; 2020, c. 663.