A. Unless otherwise provided by right, each locality shall require a special exception pursuant to §§ 15.2-2204, 15.2-2286, and 15.2-2288.7 or a siting agreement pursuant to § 15.2-2316.7 and include in its zoning ordinance regulations and provisions consistent with this section for a special exception as defined in § 15.2-2201, for any solar photovoltaic project. For the purposes of this section, "solar photovoltaic project" means a ground-mounted solar facility with a generating capacity of one megawatt or more that is designed to serve, or serves, the electricity or thermal needs of any property other than the property where such facility is located.
- 1. Setback distances shall be measured from the nearest edge of the equipment as follows: (i) between 150 and 200 feet from the nearest point on the outer wall of existing occupied community buildings and dwellings on nonparticipating properties; (ii) between 50 and 100 feet from the outside edge of the roadbed of any road abutting the property; (iii) for projects not greater than 25 megawatts, 50 feet from the edge, and for projects greater than 25 megawatts, 100 feet from the edge, of tidal wetlands or nontidal wetlands, as defined in 9VAC25-830, or from the top of bank of perennial streams, as defined in § 62.1-44.122; (iv) for projects of any capacity within Chesapeake Bay Preservation Areas, between 100 and 125 feet from the edge of tidal wetlands, nontidal wetlands, or from the top of bank of perennial streams; and (v) between 50 and 75 feet measured from the nearest shared property line for nonparticipating properties. Nothing in this subdivision shall preclude the owner of a nonparticipating property from waiving the foregoing setback requirements by written agreement. Setbacks shall not be required for internal boundaries between adjacent participating parcels. For purposes of clauses (iii) and (iv), "equipment" is limited to solar panels, racking equipment, and inverters.
- 2. Fencing for the facility shall comply with § 55.1-2804, the latest version of the National Electrical Safety Code or any applicable successor standard regarding requirements for limiting access to facilities, and the Uniform Statewide Building Code (§ 36-97 et seq.). Vegetative visual screening requirements shall not be required to exceed three feet at planting, shall be between 25 and 50 feet wide, and shall allow for consideration of preexisting natural or manmade visual barriers.
- 3. The height of solar panels shall not exceed 25 feet above ground when the arrays are at full tilt, except in cases where a height variance is necessary to allow for agrivoltaics activity below or in proximity to the panels. For purposes of this section, "agrivoltaics" means the same as that term is defined in § 10.1-1197.5.
- 4. Visual impacts of facilities on public parks, scenic rivers and byways, and historic structures or sites listed on or eligible for the National Register of Historic Places or a county register of historic places shall be minimized. A locality may request a viewshed analysis as part of the special exception application to assure that visual impacts are minimized through solar panel placement, height, landscaping, and screening. Such analysis shall account for existing vegetation and planned visual buffers. Such screening may be accomplished on any property with the consent of the property owner.
- 5. The facility shall implement light intensity dimming solution technology that provides a means of tailoring the intensity level of lights according to surrounding visibility.
- 6. The facility shall comply with all Department of Environmental Quality stormwater regulations as established in 9VAC25-880.
- 7. The facility shall minimize new impervious surface on the site and under its solar panels.
- 8. Land disturbance, including site grading, construction, and landscaping, shall be conducted in compliance with a stormwater pollution prevention plan. Topsoil shall not be removed from the project site. Topsoil shall be returned to disturbed areas from stockpiles as quickly as site conditions allow, unless returning soil would cause adverse impacts to topsoil integrity or is otherwise not practicable for construction activities. Site stabilization shall occur as the site is developed, following appropriate stabilization timelines as identified in the General VPDES Permit for Discharges of Stormwater from Construction Activities, and shall not be delayed until site construction is completed. The facility shall decompact soil as necessary and feasible for re-vegetation after construction has concluded.
- 9. When all land-disturbing activities at the construction site have been completed, the facility shall initiate permanent stabilization to provide vegetative ground cover that provides a minimum level of coverage over the project site. An ordinance may require up to 75 percent vegetative cover with no significant bare areas that is mature enough to survive and will inhibit erosion. The use of native and naturalized plants shall be encouraged and invasive plants as established pursuant to § 10.1-104.6:2 shall be prohibited. For projects or portions of projects not used for animal grazing, co-located crop production, native and naturalized pollinator plant species, or native and naturalized meadow species shall be planted, except for in the area directly beneath panels, and maintained throughout the solar project's life. The seed mix shall include a diversity of species with varied bloom times. Mowing shall be limited and performed on a schedule that promotes the establishment of the native plantings, controls invasive species, and minimizes impacts to wildlife. All trees and shrubs at the time of planting shall accommodate adequate screening or buffering at the end of five years of planting. Vegetation used to establish a visual screen shall not be trimmed to stunt upward and outward growth or to otherwise limit the effectiveness of the visual screen.
- 10. The facility shall provide for wildlife passage where needed by limiting fencing to the areas in reasonable proximity to arrays and interconnection equipment to the extent practicable and consistent with safety and security requirements. The facility shall prioritize open wildlife access to riparian areas, wetlands, streams, and other areas not in proximity to panels.
- 11. The facility shall comply with all applicable state and federal labor and employment laws, including apprenticeships and labor standards necessary to achieve any available tax credit bonuses found in 26 U.S.C. §§ 45Y and 48E.
- 12. A locality shall require an applicant to enter into a written agreement to decommission equipment, facilities, or devices pursuant to § 15.2-2241.2.
Any special exception granted pursuant to this section is an amendment to the zoning ordinance pursuant to subdivision A 7 of § 15.2-2286 and shall comply with the following criteria. Where numerical ranges are attached to criteria, localities may choose to establish an ordinance that specifies any number within the applicable range that they deem appropriate for their community. In the issuance of a special exception, a variance from these ordinance criteria may be implemented only with a written agreement of the locality, the property owner or their agent, and the applicant. Nothing in this section shall (i) be construed to relieve projects of the responsibility to comply with all relevant state and federal laws, regulations, and permits, including those related to tree canopy; (ii) require a locality to approve a special exception application considered pursuant to this section; (iii) be construed to prohibit a locality from permitting a solar photovoltaic project or energy storage project by right; or (iv) prohibit the owner of a proposed solar photovoltaic project and a locality from entering into a siting agreement that provides less stringent restrictions than those specified under this subsection.
- B. Any locality may grant a special exception pursuant to § 15.2-2286, and include in its zoning ordinance reasonable regulations and provisions for a special exception as defined in § 15.2-2201, for an energy storage project. For the purposes of this section, "energy storage project" includes energy storage equipment and technology within an energy storage project that is capable of absorbing energy, storing such energy for a period of time, and redelivering such energy after it has been stored.
- C. The governing body of such locality may grant a condition that includes (i) dedication of real property of substantial value or (ii) substantial cash payments for or construction of substantial public improvements, the need for which is not generated solely by the granting of a conditional use permit, so long as such conditions are reasonably related to the project.
- D. Once a condition is granted pursuant to subsection C, such condition shall continue in effect until a subsequent amendment changes the zoning on the property for which the conditions were granted. However, such conditions shall continue if the subsequent amendment is part of a comprehensive implementation of a new or substantially revised zoning ordinance.
- E. The governing body of such locality shall furnish the State Corporation Commission a record of special exception decisions reached pursuant to this section not more than 60 days after such decision is made. The record shall include (i) the reason for any adverse decision, (ii) any finding of nonconformity with the local comprehensive plan, and (iii) the date of the last revision to the comprehensive plan.
2020, cc. 385, 414; 2021, Sp. Sess. I, cc. 57, 58; 2026, cc. 1005, 1068.