- (1) Following construction and prior to impounding any water, the state engineer shall undertake a final inspection of the project.
(2) A written final approval of the project shall be issued if:
(a) the state engineer determines that:
- (i) the project was constructed in accordance with plans approved by the state engineer under Sections 73-5a-203 and 73-5a-303; and
- (ii) during construction, inspections and tests were conducted as required by Section 73-5a-301; and
- (b) the emergency action plan and standard operating plan meet the requirements set forth in rules adopted by the state engineer.
(3)
(a) The state engineer may require the owner to:
- (i) submit a formal operating plan for the initial filling of the reservoir; or
- (ii) follow certain procedures during the initial filling of the reservoir.
- (b) Failure to submit the operating plan or follow the specified procedures shall result in revocation of the final approval.
Enacted by Chapter 319, 1990 General Session