As used in this chapter:
- (1) "Board" means the Board of Water Resources.
(2)
- (a) "Construction costs" means all costs related to the development of a project, except the costs of environmental mitigation.
(b) Construction costs include:
- (i) planning;
- (ii) engineering and legal work;
- (iii) permitting;
- (iv) acquisition of land and rights-of-way;
- (v) rebuilding and relocation of highways or other facilities affected by the project;
- (vi) compensation for impairment of existing water rights;
- (vii) construction of the dam, reservoir, and associated facilities; and
- (viii) expenses of the division related to the project.
- (3) "Developed waters" means surface water developed by projects authorized under this chapter.
- (4) "Division" means the Division of Water Resources.
(5) "Environmental mitigation costs" means costs that may be required by federal, state, or local governmental agencies for project environmental permitting, including:
- (a) planning;
- (b) environmental and engineering studies;
- (c) permitting;
- (d) acquisition of land and rights-of-way; and
- (e) operation, maintenance, and repair of facilities associated with project environmental mitigation.
(6) "Preconstruction costs" means any of the following costs incurred before project construction begins:
- (a) planning;
- (b) design;
- (c) engineering studies;
- (d) legal work;
- (e) permitting;
- (f) acquisition of land and rights-of-way;
- (g) compensation for impairment of existing water rights;
- (h) environmental studies; or
- (i) any combination of Subsections (6)(a) through (h).
- (7) "Project costs" include preconstruction costs, construction costs, environmental mitigation costs, and costs of operation, maintenance, repair, and replacement.
Amended by Chapter 84, 2006 General Session