(1) The commission shall:
- (a) investigate a large load flexible tariff for a qualified electric utility; and
(b) adopt a large load flexible tariff if the commission determines that the tariff is:
- (i) just and reasonable; and
- (ii) in the public interest.
(2) In conducting an investigation for a large load flexible tariff, the commission shall consider:
- (a) the conditions and times for the tariff;
- (b) the means of determining the rates, terms, and conditions pursuant to which a qualified electric utility may provide electric services to a large load customer; and
- (c) the conditions under which a qualified electric utility may require a large load customer to reduce or eliminate electric usage under the large flexible load tariff.
Enacted by Chapter 318, 2025 General Session