(1) If the provision of service to a large load customer requires transmission service:
- (a) the qualified electric utility or the large-scale generation provider shall submit a transmission service request to the transmission provider;
(b) to the fullest extent allowable under applicable federal law and regulations, the large-scale generation provider or large load customer shall:
(i) pay for:
- (A) any interconnection or transmission-related studies;
- (B) any identified interconnection upgrades, transmission upgrades, network upgrades, distribution system upgrades, or system upgrades; and
- (C) the transmission service rates in the transmission provider's open access transmission tariff; and
(ii) pay and provide for:
- (A) ancillary services;
- (B) balancing services; and
- (C) backup services.
(2) Nothing in this section shall be construed to:
- (a) conflict with or supersede any applicable federal law, regulation, or order regarding transmission cost allocation; or
- (b) require cost allocation methods inconsistent with Federal Energy Regulatory Commission requirements or orders.
- (3) The commission shall review transmission cost allocation consistent with federal requirements and may establish rules for implementation of this section.
Enacted by Chapter 318, 2025 General Session