(1) A qualified electric utility or a large-scale generation provider shall file an application with the commission for approval of a large load contract that includes:
- (a) a copy of the large load contract for which the applicant seeks review and approval; and
- (b) evidence sufficient to demonstrate compliance with Subsection (2)(b).
(2) The commission shall approve a large load contract submitted under Subsection (1) if the commission finds by a preponderance of the evidence that:
- (a) the contract complies with the requirements of this chapter;
- (b) the large load customer bears all just and reasonable incremental costs attributable to receiving the requested electric service; and
- (c) existing ratepayers do not bear costs justly and reasonably attributable to providing electric service for the large load customer.
(3) Commission review of a large load contract:
- (a) is limited to the requirements described in Subsection (2); and
- (b) does not include review of other contract terms.
- (4) The commission shall approve or disapprove an application submitted under this section within 60 days after the day on which a person files the application.
- (5) The commission may establish rules to expedite the review of applications for approval of a large load contract under this chapter.
Enacted by Chapter 318, 2025 General Session