- (1) Required by the department project;
- (2) Of equivalent standards although not identical;
- (3) Of the next highest grade or size when the existing devices or materials are no longer regularly manufactured;
- (4) Required by law pursuant to governmental and appropriate regulatory commission code; or
- (5) Required by current design practices regularly followed by the Utility in its own work, and there is a resulting direct benefit to the department project.
No betterment credit is required for the replacement of utility devices or materials that are:
KEY: right-of-way, utility accommodation, utility facilities, utilities
Date of Last Change: December 11, 2024
Notice of Continuation: May 12, 2025
Authorizing, and Implemented or Interpreted Law: 54-3-29(5)(b); 54-3-29(6); 54-3-29(7); 72-6-116(2); 72-6-116(6)