- (1) Location site is selected.
- (2) Site is surveyed for location and elevation.
- (3) Selected site is submitted to the FAA for approval.
- (4) Upon receiving FAA approval, navigational aid may be installed.
- (5) After installation, navigational aid is checked and certified for operation by the FAA.
Procedure.
KEY: air traffic, aviation safety, airports, airspace
Date of Last Change: October 12, 2016
Notice of Continuation: August 23, 2022
Authorizing, and Implemented or Interpreted Law: 72-10-103; 72-10-116