1. Prior to conducting any operations that may disturb the surface of lands contained in a lease, the lessee or designated operator shall submit for approval simultaneously to the agency and to UDOGM, a plan of operations and must receive the approval of the plan by both agencies. Said plan shall include, at a minimum, all proposed access and infrastructure locations and proposed site reclamation. Prior to approval, the agency may require the lessee or designated operator to adopt a special rehabilitation program for the particular property in question. The agency will review any request for drilling operations and will grant approval provided that the contemplated location and operations are not in violation of any rules or order of the agency. Agency approval of the plan of operations
for oil, gas or hydrocarbon resources is required prior to approval by UDOGM, unless otherwise waived in writing to UDOGM by the agency.
2. Prior to approval of the plan of operations, the agency shall require the lessee or designated operator to:
4. Oil and gas drilling, or other operations which disturb the surface of the leased lands shall require surface rehabilitation of the disturbed area as prescribed and as required by the rules and regulations administered by the agency and UDOGM.
All pits, excavations, roads and pads shall be shaped to facilitate drainage and control erosion by following the best management practices. In no case shall the pits or excavations be allowed to become a hazard to persons or livestock. All material removed from the disturbed area shall be stockpiled and be used to fill the pits and for leveling and reclamation of roads and pads, unless consent of the agency to do otherwise is obtained. At the termination of the lease, the land will as nearly as practicable approximate its original configuration. All drill holes must be plugged in accordance with rules promulgated by UDOGM. All mud pits shall be filled and materials and debris removed from the site.
All topsoil in the affected area shall be removed, stockpiled, and stabilized on the leased trust lands until the completion of operations. Upon reclamation, the stockpiled topsoil will be redistributed on the affected area and the land revegetated as prescribed by the agency.
KEY: oil gas and hydrocarbons, administrative procedures, lease provisions, operations
Date of Last Change: June 1, 2019
Notice of Continuation: January 2, 2025
Authorizing, and Implemented or Interpreted Law: 53C-1-302(1)(a)(ii); 53C-2 et seq.