(1) A request for approval of a Resource decision shall include testimony and exhibits which provide:
- (a) A description of the Resource decision,
- (b) Information to demonstrate that the Energy utility has complied with the applicable requirements of the Act and Commission rules,
- (c) The purposes and reasons for the Resource decision,
- (d) An analysis of the estimated or projected costs of the Resource decision, including the engineering studies, data, information and models used in the Energy utility's analysis,
- (e) Descriptions and comparisons of other resources or alternatives evaluated or considered by the Energy utility, in lieu of the proposed Resource decision,
- (f) Sufficient data, information, spreadsheets, and models to permit an analysis and verification of the conclusions reached and models used by the Energy utility,
- (g) An analysis of the estimated effect of the Resource decision on the Energy utility's revenue requirement,
(h) Financial information demonstrating adequate financial capability to implement the Resource decision,
- (i) Major contracts, if any, proposed for execution or use in connection with the Resource decision,
- (j) Information to show that the Energy utility has or will obtain any required authorizations from the appropriate governmental bodies for the Resource decision, and
- (k) Other information as the Commission may require.
(2) Notice of a request for approval of a Resource decision.
- (a) At least five calendar days prior to filing a request for approval of a Resource decision, the Energy utility shall provide public notice of its request for approval of a Resource decision. The public notice shall provide a description of the request and information on how interested persons my obtain, from the Energy utility, further information about the request or a copy of the request.
- (b) At least five calendar days prior to filing a request for approval of a Resource decision, the Energy Utility shall inform the Commission of the anticipated filing and the means by which the Energy Utility has made, or will make, the public notice.
- (3) Issues regarding the production, treatment and use of materials of a confidential or proprietary nature, including issues regarding who is entitled to review the materials, will be determined by the Commission.
KEY: resource decision, energy utility, filing requirements
Date of Last Change: March 19, 2007
Notice of Continuation: January 27, 2022
Authorizing, and Implemented or Interpreted Law: 54-17-100 et seq.