- (1) The Commission shall approve or disapprove an application for approval of a large load contract within 60 days of the application being filed.
(2) The Commission shall approve an application for a large load contract if the Commission finds:
- (a) the contract complies with Title 54, Chapter 26, Large-Scale Electric Service Requirements;
- (b) the large load customer bears each just and reasonable incremental cost attributable to receiving the requested electric service; and
- (c) existing ratepayers do not bear costs justly and reasonably attributable to providing electric service for the large load customer.
KEY: public utilities, large-scale electric service requirements
Date of Last Change: January 1, 2026
Authorizing, and Implemented or Interpreted Law: 54-26-302(5); 54-26-503(3); 54-26-504(4); 54-26-901(1)(a)