- (1) On October 1, 2025, and by the same date each year thereafter, a qualified utility shall file a status report with the Commission regarding the qualified utility's implementation of its Electrical Power Delivery Quality Plan.
- (2) Upon filing of the status report, the Commission shall promptly issue a public notice of filing and comment period, inviting any interested person to submit written comments to the Commission within 30 days of the date the Commission issues the notice.
- (3) From the date public comments are due, the qualified utility shall have 21 days to file a written response with the Commission.
(4) Within 90 days of the date a qualified utility submits a status report regarding its Electrical Power Delivery Quality Plan, the Commission shall:
- (a) issue a letter acknowledging the qualified utility's status report satisfies and complies with the requirements of this rule;
- (b) issue a letter indicating the Commission declines to acknowledge the status report complies with the requirements of this rule and explaining the basis for the Commission's determination; or
- (c) issue an order directing any further process the Commission finds necessary and in the public interest to ensure a qualified utility is reasonably implementing its approved Electrical Power Delivery Quality Plan.
- (5) Notwithstanding Subsections R746-316-5(1) through R746-316-5(4), the Commission may extend the time for public comment, the time for a qualified utility to respond to public comment, or the time allowed for the Commission to act on a status report provided the Commission determines that additional time or process is warranted and in the public interest.
KEY: public utilities; electrical power delivery quality
Date of Last Change: October 26, 2023
Authorizing, and Implemented or Interpreted Law: 54-25-101; 54-25-102; 54-25-201