- (1) Based on the grant applications submitted under Section R653-10-4 and prioritization of those applications performed by the division under Section R653-10-5, the board may award a grant to a qualified applicant for installing secondary water use meters, subject to the requirements and conditions of this rule.
(2)(a) As a condition to receiving a grant under this section, the applicant shall enter into a contract with the board for use of the grant money.
(b) The contract with the board shall be executed no later than December 31, 2024 and require that grant funds are:
- (i) committed through contract no later than December 31, 2024; and
- (ii) completely spent and the project completed under the term of the grant no later than December 31, 2026.
- (c) Nothing in Subsection (2) limits the division or board from including additional terms and conditions in the grant contract.
KEY: secondary water meter funding
Date of Last Change: June 1, 2022
Authorizing, and Implemented or Interpreted Law: 73-10