Utah Admin. Code R652-100-1000
1. Prior to the commencement of any activity authorized by a materials permit the permittee shall be required to submit, for the director's approval, a plan of operations which shall include the following:
(a) A map or plat showing
i) the location and sequence of areas from which material is to be excavated;
ii) the location of any processing or stationary equipment or improvements which will be placed on the premises;
iii) transportation and access routes across the premises and adjacent properties;
iv) the location of any fuel storage tanks; and,
v) the location of stockpile areas.
KEY: administrative procedure, materials handling, permits
Date of Last Change: 1993
Notice of Continuation: March 8, 2022
Authorizing, and Implemented or Interpreted Law: 65A-7-1