- (1) Division personnel shall be given a reasonable opportunity for inspection of any E and P recycling facility during the construction and operation of the facility.
- (2) The division shall be notified at least 72 hours before the installation of leak detection systems or liners.
- (3) The division shall be notified after completion of facility construction so that a final inspection can be conducted to verify that the facility has been constructed in accordance with the approved application.
- (4) Failure to meet the requirements and standards for construction and operation of a E and P recycling facility shall be considered as noncompliance and will result in the imposition of corrective actions and compliance schedules or a cessation of operations order.
KEY: oil and gas law
Date of Last Change: February 26, 2025
Notice of Continuation: June 30, 2025
Authorizing, and Implemented or Interpreted Law: 40-6-5(3)