- (1) Planned Changes: The operator shall give notice to the division as soon as possible of any planned physical alterations or additions to the permitted CO2 Sequestration facility.
- (2) Notice of Well Completion: An injection well may not commence injection until construction is complete, a notice of completion has been submitted to the division, the division has inspected or otherwise reviewed the injection well and finds it is in compliance with the conditions of the permit, and the division has given approval to begin injection.
- (3) Anticipated Noncompliance: The operator shall give advance notice to the division of any planned changes in the permitted CO2 Sequestration facility or activity that may result in noncompliance with permit requirements.
- (4) Transfers: A permit is not transferable to any person except after notice to the division and approval by the board. The division may require modification or revocation and reissuance of the permit to change the name of the owner or operator and incorporate such other requirements as may be necessary under the Safe Drinking Water Act and Section R644-7-5.
- (5) Compliance Schedules: Report of compliance or noncompliance with, or any progress reports on, interim and final requirements contained in any compliance schedule in this rule shall be submitted to the division no later than 14 days following each compliance schedule date.
- (6) The operator shall notify the division at such times as the permit requires before conversion or abandonment of the well or before closure of the project.
- (7) Other Noncompliance: The operator shall report any instance of noncompliance not reported under Subsection (5) and Subsection R644-15-1(1)(d) when quarterly reports are submitted. The reports shall contain the information listed in Subsection R644-15-1(d)(i).
- (8) Other Information: Where the operator becomes aware that they failed to submit any relevant facts in a permit application, or submitted incorrect information in a permit application or in any report to the division, they shall promptly submit such facts or information.
KEY: oil and gas law
Date of Last Change: July 31, 2025
Authorizing, and Implemented or Interpreted Law: 40-11-3