- (1) Following a grant award by the Commission, the department shall assist each grantee in identifying sources and securing additional funding for the project, as outlined in Subsection 73-10g-206(5)(c).
(2) Before receiving funds, a grantee shall fulfill the following requirements, consistent with Subsection 73-10g-206(3) by:
(a) entering a contract with the department that includes the following:
- (i) the expectations for the grantee;
- (ii) the life expectancy of the project;
- (iii) the process to certify completion of the project;
- (iv) any applicable design requirements; and
- (v) metering and reporting requirements consistent with rules established by DWRi, including specifications for the type of meter to be installed;
- (b) filing any necessary change application with DWRi;
- (c) if applicable, obtaining a final order from the State Engineer approving the change application; and
- (d) if applicable, demonstrating compliance with the requirements of the final order.
(3)(a) Before project implementation, grantees shall submit a Utah State Historical Preservation Office Cultural Resource Review report to the department, pursuant to Section 9-8a-404.
- (b) The department may not process a payment reimbursement until the department receives the report.
- (4) The department may issue a notice to proceed to a grantee before project construction.
(5) During the life of the project, the department shall:
- (a) monitor grant related activities; and
- (b) certify project completion.
- (6) The department may conduct on-site or virtual project "spot checks" at any time during the life of the project.