- (1) Inspections or tests shall be performed so as not to unduly delay the work of the contractor or subcontractor. No inspector may change the specifications or the contract without written authorization of the procurement official. The presence or absence of an inspector or an inspection may not relieve the contractor or subcontractor from any requirements of the contract.
- (2) When an inspection is made, the contractor or subcontractor shall provide without charge all reasonable facilities and assistance for the safety and convenience of the person performing the inspection or testing.
KEY: terms and conditions, contracts, change orders, costs
Date of Last Change: October 22, 2024
Authorizing, and Implemented or Interpreted Law: 63G-6a-107.7(1); 63G-6a-1202; 63G-6a-1204; 63G-6a-1205; 63G-6a-1207; 63G-6a-1208; 63G-6a-1209