- A. Any new system installed after April 2009 must have a written operation and maintenance manual document describing the treatment and disposal system and outlining routine maintenance procedures, including checklists and maintenance logs needed for proper operation of the system.
- B. Each LUWD Conventional System shall be assessed after the first year of operation and annually thereafter.
- C. Each LUWD Pressure Distribution System shall be inspected as outlined in Section R317-4-23 Tables 7.1 and 7.2.
D. LUWD Alternative Systems.
- 1. Each alternative system shall be inspected as outlined in Section R317-4-13 Tables 7.1 and 7.2.
2. Each packed bed media system shall be sampled a minimum of every six months as outlined in Section R317-4-13 Table 7.3.
- a. The grab sample shall be taken before discharge to an absorption system.
- b. Effluent not meeting the standards of Section R317-4-13 Table 7.3, shall be followed with two successive weekly tests of the same type within a 30 day period from the first exceedance.
- 3. If two successive samples exceed the minimum standards, the system shall be deemed to be malfunctioning, and shall require further evaluation and a corrective action plan, see Subsection R317-5-3.9.
9.1. Operation and maintenance shall be provided by the owner to ensure the disposal system is functioning properly at all times.
9.2. The owner is responsible for maintaining a LUWD system and for performing periodic inspections, servicing and monitoring of its system as detailed in the issued operating permit, including the following:
KEY: water pollution, large underground wastewater, sewerage, engineering
Date of Last Change: March 26, 2014
Notice of Continuation: April 7, 2022
Authorizing, and Implemented or Interpreted Law: 19-5