Utah Admin. Code R317-5-10
C. A summary of any enforcement actions taken, identifying those actions that are still pending, and those that been resolved.
10.3. Annual Inspection Report.
The owner of a LUWD system shall summit an annual inspection report covering the period of July 1 to June 30, the "reporting year", to the permitting agency no later than August 1 of each year. In this report, the owner shall report on all requirements listed in the operating permit. As a minimum, the report shall include the following items:
E. Checklist of inspections performed including the date of the inspection and a list of findings. The report must include, where pertinent:
10.1. Operating Permit required.
An operating permit is required for all LUWD systems to monitor that proper operation and maintenance is occurring for the protection of the environment and public health. The operating permit shall be issued by the director or, by delegated authority, the local health department having jurisdiction, and shall be effective for a period not to exceed 5 years from the date of issuance.
10.2. Local Health Department Authority to Issue Operating Permits.
Local health departments may request delegated authority to administer the operating permit program. The request must include an agreement to implement and enforce inspection, servicing, monitoring, and reporting requirements of this rule. The local health department must submit an annual report on or before September 1 of each calendar year, to the division containing:
KEY: water pollution, large underground wastewater, sewerage, engineering
Date of Last Change: March 26, 2014
Notice of Continuation: April 7, 2022
Authorizing, and Implemented or Interpreted Law: 19-5