- (a) New CCR surface impoundments and lateral expansions of existing and new CCR surface impoundments shall be designed, constructed, operated, and maintained with either a composite liner or an alternative composite liner that meets the requirements of Subsection R315-319-70(b) or R315-319-70(c).
- (b) Any liner specified in Section R315-319-72 shall be installed to cover any surrounding earth likely to be in contact with CCR. Dikes may not be constructed on top of the composite liner.
- (c) Before construction of the CCR surface impoundment or any lateral expansion of a CCR surface impoundment, the owner or operator shall obtain certification from a qualified professional engineer that the design of the composite liner or, if applicable, the design of an alternative composite liner complies with the requirements of Section R315-319-72.
- (d) Upon completion, the owner or operator shall obtain certification from a qualified professional engineer that the composite liner or if applicable, the alternative composite liner has been constructed in accordance with the requirements of Section R315-319-72.
- (e) The owner or operator of the CCR unit shall comply with the recordkeeping requirements specified in Subsection R315-319-105(f), the notification requirements specified in Subsection R315-319-106(f), and the internet requirements specified in Subsection R315-319-107(f).
KEY: permit, solid waste, coal ash
Date of Last Change: September 15, 2025
Notice of Continuation: June 16, 2026
Authorizing, and Implemented or Interpreted Law: 19-6-108