- (1) Any recycling or composting facility shall meet the requirements of Section R315-302-2, and shall submit a general plan of operation and such other information as requested by the Director prior to the commencement of any recycling operation.
- (2) Each applicable recycling or composting facility shall submit a certification that the facility has, during the past year, operated according to the submitted plan of operation to the Director by March 1 of each year.
(3) Any facility storing materials in outdoor piles for the purpose of recycling shall be considered to be disposing of solid waste if:
- (a) at least 50% of the material on hand at the beginning of a year at the facility has not been shown to have been recycled by the end of that year and any material has been on-site more than two years unless a longer period is approved by the Director; or
- (b) ground water or surface water, air, or land contamination has occurred or is likely to occur under current conditions of storage.
- (c) Upon a determination by the Director or his authorized representative that the limits of Subsection R315-312-2(3)(a) or (b) have been exceeded, the Director may require a permit application and issuance of a permit as a solid waste disposal facility.
- (4) Any recycling or composting facility may be required to provide financial assurance for clean-up and closure of the site as determined by the Director.
- (5) Tires stored in piles for the purpose of recycling at a tire recycling facility shall be subject to the requirements of Section R315-314-3.
KEY: solid waste management, waste disposal
Date of Last Change: November 20, 2023
Notice of Continuation: November 30, 2022
Authorizing, and Implemented or Interpreted Law: 19-6-105; 19-6-108