- (1) Each application for a landtreatment disposal facility permit shall contain the information required in Section R315-310-3.
(2) Each application for a permit shall also contain:
- (a) a geohydrological assessment of the facility site that addresses all of the factors of Subsection R315-310-4(2)(b);
(b) engineering report, plans, specifications, and calculations that address:
- (i) how the proposed facility will meet the location standards pursuant to Section R315-302-1;
- (ii) how the proposed facility will meet the standards of Rule R315-307;
- (iii) the basis for calculating the facility's life;
- (iv) waste analyses and methods to periodically sample and analyze solid waste;
- (v) design of interim waste storage facilities;
- (vi) design of run-on and run-off control systems;
- (vii) a contour map of the active area showing contours to the nearest foot;
- (viii) a ground water and surface water monitoring program; and
- (ix) access barriers such as fences, gate, and warning signs.
(c) a plan of operation that in addition to the requirements of Section R315-302-2 addresses:
- (i) operation and maintenance of run-on and run-off control systems;
- (ii) methods of taking ground water samples and for maintaining ground water monitoring systems; and
- (iii) methods of applying wastes to meet the requirements of Section R315-307-3.
(d) closure plan to address:
- (i) closure schedule;
- (ii) capacity of site in volume and tonnage; and
- (iii) final inspection by regulatory agencies.
(e) post-closure plan to address:
- (i) estimated time period for post-closure activities;
- (ii) site monitoring of ground water;
- (iii) changes in record of title;
- (iv) maintenance activities to maintain cover and run-off system;
- (v) plans for food-chain crops, if any, being grown on the active areas, after closure; and
- (vi) identification of final closure costs including cost calculations and the funding mechanism.
KEY: solid waste management, waste disposal
Date of Last Change: September 15, 2025
Notice of Continuation: November 30, 2022
Authorizing, and Implemented or Interpreted Law: 19-6-105; 19-6-108; 19-6-109; 40 CFR 258