(1) The director shall issue a certificate of compliance to an owner or operator for individual petroleum storage tanks at a facility if:
- (a) the owner or operator has a certificate of registration;
- (b) the owner or operator must certify that the PST is in substantial compliance with state and federal statutes, rules, and regulations applicable to PST systems;
- (c) the tank tightness test, as required by Section 19-6-413 conducted within six months before the tank was registered or within 60 days after the date the tank was registered, indicates that each individual PST is not leaking;
- (d) the owner or operator has submitted a letter to the director stating that based on customary business inventory practices standards there has been no release from the tank;
- (e) the owner or operator has submitted a completed application according to a form provided and approved by the director, and participates in the EAP or demonstrates that the financial assurance that will be used meets the requirements of Subsection R311-206-2(1)(b) and Section R311-206-5;
- (f) the owner or operator has met the requirements for the financial assurance mechanism chosen, including payment of applicable fees;
- (g) the owner or operator has submitted an as-built drawing, for newly-installed systems, that meets the requirements of Subsection R311-200-1(2)(d) or a site plat, for existing systems, that meets the requirements of Subsection R311-200-1(2)(jjj); and
- (h) the owner or operator has, for newly-installed tanks, submitted the completed tank manufacturer's installation checklist.
KEY: petroleum, underground storage tanks
Date of Last Change: September 16, 2025
Notice of Continuation: March 8, 2022
Authorizing, and Implemented or Interpreted Law: 19-6-105; 19-6-403; 19-6-410.5; 19-6-428