- (1) Completeness Determination. Within 30 days after receipt of a notice of intent, or any additional information necessary to the review, the director will advise the applicant of any deficiency in the notice of intent or the information submitted.
(2) Within 90 days after the receipt of a complete application including the information described in Section R307-401-5, the director will:
- (a) issue an approval order for the proposed construction, installation, modification, relocation, or establishment pursuant to the requirements of Section R307-401-8; or
- (b) issue an order prohibiting the proposed construction, installation, modification, relocation or establishment if it is determined that any part of the proposal will not be in accord with the requirements of Title R307.
- (3) The review period under Subsection R307-401-6(2) may be extended by up to three 30-day extensions if more time is needed to review the proposal.
KEY: air pollution, permits, approval orders, greenhouse gases
Date of Last Change: December 19, 2025
Notice of Continuation: May 4, 2022
Authorizing, and Implemented or Interpreted Law: 19-2-104(3)(b)(iii); 19-2-108