Utah Admin. Code R307-401-18
Approval orders issued by the director in accordance with Rule R307-401 will be reviewed 18 months after the date of issuance to determine the status of construction, installation, modification, relocation, or establishment. If a continuous program of construction, installation, modification, relocation, or establishment is not proceeding, the director may revoke the approval order.
KEY: air pollution, permits, approval orders, greenhouse gases
Date of Last Change: December 19, 2025
Notice of Continuation: May 4, 2022
Authorizing, and Implemented or Interpreted Law: 19-2-104(3)(b)(iii); 19-2-108