(1) An owner or operator of an asphalt plant shall comply with the following:
- (a) ensure opacity does not exceed 10% opacity and opacity observations shall be conducted in accordance with 40 CFR 60, Method 9;
- (b) use natural gas, propane, fuel oil, on-specification used oil as defined in Rule R315-15, or any combination thereof as fuel;
- (c) maintain records of fuel use;
- (d) control particulate emissions from each storage silo with a fabric filter, a baghouse, a bin vent, or a dust collector;
- (e) control particulate emissions from each asphalt mixer with a baghouse;
(f) maintain the pressure drop of the asphalt plant baghouse between 3.0 and 7.0 inches of water during operation and additionally the owner or operator shall comply with the following:
- (i) install a pressure gauge on each baghouse;
- (ii) ensure the pressure gauge measures the pressure drop in 1-inch water column increments or less;
- (iii) calibrate the pressure gauge according to the manufacturer's instructions at least once every 12 months; and
- (iv) record the reading of the pressure gauge at least once per operating day.
(2) The owner or operator shall:
- (a) ensure filterable PM2.5 emissions do not exceed 0.024 grains per dry standard cubic foot;
- (b) conduct an initial stack test on each asphalt plant within 180 days after startup;
- (c) conduct a stack test on each asphalt plant within three years after the date of the most recent stack test;
- (d) conduct stack testing according to Rule R307-165; and
- (e) determine PM2.5 emissions by 40 CFR 60, Appendix A, Method 5.
KEY: air pollution, permits, approval orders, greenhouse gases
Date of Last Change: March 31, 2025
Authorizing, and Implemented or Interpreted Law: 19-2-104(3)(b)(iii); 19-2-108