Utah Admin. Code R23-5-9
The division may utilize the project reserve only for the award of construction contracts which exceed the available construction budget. This may only be done after a review of other options to bring the cost within available funding and a determination that this action is necessary to meet the intent of the project.
KEY: buildings, contingency fund
Date of Last Change: February 8, 2023
Notice of Continuation: August 30, 2022
Authorizing, and Implemented or Interpreted Law: 63A-5b-609