- (1) An agency shall receive approval from the director before the agency begins programming for a new facility that requires legislative approval under Section 63A-5b-404.
- (2) When requesting the director's approval, the agency shall justify the need for initiating the programming process at that point in time and also address the level of support for funding the project soon after the program document is completed.
- (3) The director may approve the programming of a new facility before the Legislature makes an appropriation for the new facility under Subsection 63A-5b-406(4)(c). When the program is funded by the agency, programming funds may be reimbursed from an appropriation if, at a later time, the Legislature funds the programming.
KEY: planning, public buildings, design, procurement
Date of Last Change: October 2, 2025
Notice of Continuation: February 7, 2024
Authorizing, and Implemented or Interpreted Law: 63A-5b-305; 63A-5b-402