10 U.S.C. § 7301
(a) In General.— The delivery of a covered vessel shall be deemed to occur on the date on which—
(b) Inclusion in Budget and Acquisition Reports.— The delivery dates of covered vessels shall be included—
(Added Pub. L. 114–328, div. A, title I, § 121(a)(1), , 130 Stat. 2029.)
The date of the enactment of this section, referred to in subsec. (c), is the date of enactment of Pub. L. 114–328, which was approved .
A prior section 7301, act Aug. 10, 1956, ch. 1041, 70A Stat. 450, related to estimates required for bids on construction of naval vessels, prior to repeal by Pub. L. 103–160, div. A, title VIII, § 824(a)(7), , 107 Stat. 1707.
Pub. L. 114–328, div. A, title I, § 121(b), , 130 Stat. 2030, provided that:
“(1) In general.— Not later than , the Secretary of the Navy shall certify to the congressional defense committees [Committees on Armed Services and Appropriations of the Senate and the House of Representatives] that the delivery dates of the following vessels have been adjusted in accordance with section 7301 of title 10, United States Code, as added by subsection (a):
- “(A) The U.S.S. John F. Kennedy (CVN–79).
- “(B) The U.S.S. Zumwalt (DDG–1000).
- “(C) The U.S.S. Michael Monsoor (DDG–1001).
- “(D) The U.S.S. Lyndon B. Johnson (DDG–1002).
- “(E) Any other vessel of the Navy that is under construction on the date of the enactment of this Act [].
“(2) Contents.— The certification under paragraph (1) shall include—
- “(A) an identification of each vessel for which the delivery date was adjusted; and
- “(B) the delivery date of each such vessel, as so adjusted.”