- (a) The permittee shall notify the appropriate Texas Commission on Environmental Quality (TCEQ) regional office at least 30 days prior to the date field layout and/or construction startup is scheduled to begin.
- (b) If soils are to be imported, the permittee shall notify the TCEQ regional office at least 30 days prior to completion of the soil importing project.
- (c) The permittee shall notify the appropriate TCEQ regional office at least 30 days prior to the date that construction is projected to be complete.
- (d) The permittee shall notify the appropriate TCEQ regional office within 30 days after operation of the subsurface area drip dispersal system begins.
Source Note:The provisions of this §222.43 adopted to be effective July 5, 2006, 31 TexReg 5308.