- (a) Blowdown water from power boilers must pass through an approved blowdown separator or blowdown tank when entering a sanitary sewer.
- (b) The temperature of the blowdown water leaving the blowdown separator or blowdown tank must not exceed 140 degrees Fahrenheit.
- (c) The pressure of the blowdown water leaving a blowdown separator or blowdown tank must not exceed 5 PSIG.
- (d) All blowdown piping and fittings must meet requirements set forth in ASME Piping Code B31.1, Power Piping.
- (e) A blowdown separator must be fitted with threaded or flanged openings to facilitate inspection. A blowdown tank must be fitted with a manway for cleaning and inspection.
- (f) The vent and drain of the blowdown separator or blowdown tank must be piped to a safe point of discharge.
(g) A blowdown separator or blowdown tank, when required by this chapter, must:
- (1) be constructed in accordance with ASME Boiler and Pressure Vessel Code, Section VIII Division 1;
- (2) have a minimum design pressure equal to the recommended pressure of the boiler manufacturer for the boiler to which the tank or separator is connected; and
- (3) be registered with the National Board of Boiler and Pressure Vessel Inspectors.
- (h) Installation or modification of equipment to achieve compliance with this section is required to be completed no later than June 1, 2025.
Source Note:The provisions of this §65.555 adopted to be effective December 1, 2024, 49 TexReg 9511.