- (a) Except as provided by Section 33.024, an electric utility may not change its rates unless the utility files a statement of its intent with the regulatory authority that has original jurisdiction over those rates at least 35 days before the effective date of the proposed change.
- (b) The electric utility shall also mail or deliver a copy of the statement of intent to the appropriate officer of each affected municipality.
(c) The statement of intent must include:
- (1) proposed revisions of tariffs; and
(2) a detailed statement of:
- (A) each proposed change;
- (B) the effect the proposed change is expected to have on the revenues of the utility;
- (C) each class and number of utility consumers affected; and
- (D) any other information required by the regulatory authority's rules.
Acts 1997, 75th Leg., ch. 166, Sec. 1, eff. Sept. 1, 1997.