Each registrant shall:
- (1) Test all safety and warning devices including interlocks at intervals not to exceed 3 months to determine that they are functioning properly;
- (2) In conjunction with initial operation and after changes have been made in shielding, operating parameters, equipment, or occupancy of adjacent areas, make a survey as required in Rule 0400-20-05-.70;
- (3) Test any interlock which has been bypassed or otherwise prevented from operation, when such interlock is returned to use, to determine if it is functioning properly; and
- (4) Have a survey made of each radiation area upon the initial entry by personnel into these areas following the operation of accelerator. The registrant shall not be required to make a record of the survey required by this paragraph.
Authority: T.C.A. §§ 4-5-201, et seq.; 68-202-101, et seq.; and 68-202-201, et seq. Administrative History: Original rule filed February 22, 2012; effective May 22, 2012.