ARSD 74:56:01:23.01
Owners and operators of UST systems with spill and overfill prevention equipment and containment sumps used for interstitial monitoring of piping must meet these requirements to ensure the equipment is operating properly and will prevent releases to the environment:
(1) Spill prevention equipment (such as a catchment basin, spill bucket, or other spill containment device) and containment sumps used for interstitial monitoring of piping must prevent releases to the environment by meeting one of the following:
(b) The spill prevention equipment and containment sumps used for interstitial monitoring of piping are tested at least once every three years to ensure the equipment is liquid tight by using vacuum, pressure, or liquid testing in accordance with one of the following criteria:
(3) Owners and operators must begin meeting these requirements as follows:
(4) Owners and operators must maintain records as follows (in accordance with § 74:56:01:23 for spill prevention equipment, containment sumps used for interstitial monitoring of piping, and overfill prevention equipment:
(b) For spill prevention equipment and containment sumps used for interstitial monitoring of piping not tested every three years, documentation showing that the prevention equipment is double walled and the integrity of both walls is periodically monitored must be maintained for as long as the equipment is periodically monitored.
Note to paragraphs (1)(b) and (2). The following code of practice may be used to comply with paragraphs (a)(1)(ii) and (a)(2) of this section: Petroleum Equipment Institute Publication RP1200, "Recommended Practices for the Testing and Verification of Spill, Overfill, Leak Detection and Secondary Containment Equipment at UST Facilities''.
Source: 44 SDR 192 , effective June 28, 2018 .
General Authority: SDCL 34A-2-93, 34A-2-99, 34A-2-101.
Law Implemented: SDCL 34A-2-9 8 , 34A-2-99, 34A-2-101.