ARSD 74:36:07:110
74 : 36 : 07 : 110 . Initial control system performance test for existing municipal solid waste landfill. The owner or operator must conduct an initial performance test to be completed no later than one hundred eighty days after the initial startup of the approved control system. The performance test is not required for boilers and process heaters with design heat input capacities equal to or greater than forty-four megawatts that burns the landfill gas. The owner or operator must use the following test methods:
(2) 40 C.F.R. Part 60, Appendix A, Method 25 or 25C (July 1, 2024) must be used to determine compliance with the ninety-eight percent by weight efficiency or the twenty parts per million by volume outlet nonmethane organic compound concentration level, unless another method to demonstrate compliance has been approved by the secretary. Method 25C may be used at the inlet only. 40 C.F.R. Part 60, Appendix A, Method 3, 3A, or 3C (July 1, 2024) must be used to determine oxygen for correcting the nonmethane organic compound concentration as hexane to three percent. In cases where the outlet concentration is less than fifty parts per million nonmethane organic compound as carbon, eight parts per million nonmethane organic compound as hexane, 40 C.F.R. Part 60, Appendix A, Method 25A (July 1, 2024) should be used in place of Method 25. 40 C.F.R. Part 60, Appendix A, Method 18 (July 1, 2024) may be used in conjunction with Method 25A on a limited basis or Method 3C may be used to determine methane. The methane as carbon should be subtracted from the Method 25A total hydrocarbon value as carbon to give nonmethane organic compound concentration as carbon. The owner or operator must divide the nonmethane organic compound concentration as carbon by six to convert the nonmethane organic compound concentration as carbon to nonmethane organic compound concentration as hexane. The following equation is used to calculate efficiency:
Control efficiency=(NMOCin - NMOCout)/NMOCin, where
NMOCin = Mass of nonmethane organic compounds entering control device; and
NMOCout = Mass of nonmethane organic compounds exiting control device;
Within sixty days after the date of completing each performance test, the owner or operator must submit the results of the performance tests, including any associated fuel analyses, to the secretary.
Source: 46 SDR 64, effective November 25, 2019 ; 52 SDR 27, effective September 17, 2025 .
General Authority: SDCL 34A-1-6 , 34A-1-18 .
Law Implemented: SDCL 34A-1-18 .
Prior versions effective: 2019-11-25.