The board, through permit conditions, may authorize the department to approve proposed technical revisions to the injection well portion of an in situ leach mine without the requirement of a permit amendment. In addition to the list of technical revisions in § 74:29:03:16, in situ leach mine permit technical revisions may include the following:
(8) Delay the plugging requirement of subdivision 74:29:11:18(4) for an unused well.
In situ leach mine permit technical revision applications must comply with the procedural requirements of § 74:29:03:16, as applicable.
The applicant or an interested person may appeal the decision of the department to the board by petitioning for a contested case hearing pursuant to chapter 74:09:01.
Source: 33 SDR 160, effective April 17, 2007.
General Authority: SDCL 45-6B-81.