All mining operations must comply with the general requirements in §§ 74:29:07:02 to 74:29:07:17, inclusive, and with the following requirements:
- (1) Reclamation must rehabilitate the affected land to a condition that meets the selected postmining land use;
- (2) All reclamation activities are subject to the concurrent, interim, and final reclamation requirements of chapter 74:29:08; and
- (3) All reclamation required by the approved reclamation plan must be completed prior to final and full bond release.
Source: 14 SDR 111, effective March 3, 1988.
General Authority: SDCL 45-6B-81.
Law Implemented: SDCL 45-6B-25 , 45-6B-45.