ARSD 74:29:05:18
The operator must give the department written notice of intent to implement land application at least one week before the initiation of the land application cycle. The notice must include the following:
(4) The chemical characterization of the solution prior to treatment.
In emergency situations requiring land application, the operator must notify the department by telephone before starting land application.
Source: 14 SDR 111, effective March 3, 1988.
General Authority: SDCL 45-6B-81.
Law Implemented: SDCL 45-6B-39 , 45-6B-41 , 45-6B-44 , 45-6B-45.