ARSD 74:27:08:05
An applicant proposing to construct a new Type I or IIA facility shall schedule a presubmission meeting with the secretary at least 30 days before submittal of the Phase I application. Other applicants may schedule meetings with the secretary to discuss general and technical application requirements, including the site characterization required by chapter 74:27:12, in advance of permit application preparation.
Source: 17 SDR 8, effective July 26, 1990; 19 SDR 186, effective June 10, 1993.
General Authority: SDCL 34A-6-1.6.
Law Implemented: SDCL 34A-6-1.6 , 34A-6-1.8.